Rodina LIVING



Highway PPP projects go on, despite complications
NA, By Jana Liptáková

Highway PPP projects go on, despite complicationsConstruction of the Banská Bystrica’s bypass is part of the so-called second PPP package. Photo: Sme – Ján Krošlák

Slovakia is placing a lot of hope in its public-private partnership (PPP) projects to build highways. Not only are these intended finally to link the east and west of the country with an unbroken multi-lane highway and hence bring new business opportunities eastwards, but they should also provide orders for construction companies, thus helping to keep them afloat and their workers employed. However, the economic crisis has slowed down and complicated the whole process.

 

“Slovakia undertook preparation for highway PPP projects as early as 2007, when intensive preparation of public procurement for concessionaires for three PPP packages started,” Irma Chmelová, executive director of the PPP Association, told The Slovak Spectator. “The financial crisis, which has significantly changed conditions for provision of loans on the market, has complicated the situation.”

 

Of the three PPP packages for highway construction in Slovakia, the so-called second package was the first to achieve financial close, in August 2009. The project covers financing, construction, operation and maintenance of sections of the R1 dual-carriageway, specifically Nitra-Selenec, Selenec-Beladice, Beladice-Tekovské Nemce and the northern bypass around Banská Bystrica. The financial structure of the PPP contract, which will continue for more than 30 years, represents a total value of over €1.7 billion. Shareholders in Granvia, the consortium awarded the contract, will contribute €149 million, the European Bank for Reconstruction and Development is contributing €200 million and the rest is being provided by 12 banks. Under this project, the consortium will build a total of 52 kilometres of the dual-carriageway. Based on the concession contract with Granvia, the state will pay the consortium for construction of the sections and, after completion, their operation and maintenance for the following 30 years.

 

Construction work started in September 2009 and the individual sections should gradually be put into operation during 2011 and 2012. They are scheduled to be completely approved for public use by the end of January 2013.

 

According to Chmelová, the project also won a prestigious award from PFI magazine, the PFI Award in the category Infrastructure Deal of the Year in Europe, where it succeeded despite stiff competition.

 

“Compared with the pre-crisis situation banks are more cautious, they are lending less, for a shorter period of time and at higher interest,” Chmelová told The Slovak Spectator. “On the other hand, PPP projects’ contracts contain a provision on refinancing based on which, in case conditions for financing improve in the future, the more expensive financing will be replaced by cheaper [financing].”

 

The financial crisis has also resulted in stronger involvement by international financial institutions such as the European Investment Bank and the European Bank for Reconstruction and Development in PPP projects, according to Chmelová.

 

“Even though there are signals that the situation in financial markets is improving, it is necessary to wait for confirmation of these indications in real transactions,” she said.

 

After a number of postponements the next deadline for the financial close of another PPP package, this one known as the first PPP package, is the end of April. This is because the concessionaire, Slovenské Diaľnice, has so far failed to obtain financing for the project to construct 75 kilometres of the D1 highway, from Dubná Skala (near Vrútky) to Svinia (Prešov district), according to the SITA newswire. However, preparatory work on the sections has already started and will continue.

 

“Certain complications have occurred in negotiation over some problems and provisions with the European Commission and subsequently the European Investment Bank,” said Minister of Transport, Postal Services and Telecommunications Ľubomír Vážny, as quoted by SITA, after a March 3 cabinet session which agreed to the postponement of the financial close until the end of April.

 

The postponement relates to environmental issues arising from revision of the Environmental Impact Assessment Act.

 

The Slovak parliament adopted the revision, into which the Environment Ministry incorporated comments from the European Commission, which had objected to discrimination against private persons expressing their views on the environmental impact of large construction projects, on March 9.

 

Based on this revision, the public will have more space for participation in the approval process of some public and private projects. After the revision becomes effective, some private individuals, corporate entities, civil initiatives and associations and organisations supporting environmental protection will be able to have a say in environmental projects, something which was previously partially restricted. However, environmental organisations complain that within the amending proposals, parliament approved a provision cancelling completely the right of the public to obtain information about approval of nuclear power plants and equipment, according to SITA.

 

The European Investment Bank is supposed to provide €1 billion for the first PPP highway project, while an additional €2.5 billion is needed from private banks, according to the Pravda daily.

 

Transport Minister Vážny signed the concession agreement with representatives of the Slovenské Diaľnice consortium, led by French company Bouygues Travaux Publics SA, in April 2009. The project’s sections of the D1 highway, connecting Bratislava with Košice via the so-called northern route, should be put into trial operation by July 2013.

 

The concession agreement for construction of other D1 sections via the third PPP package was signed on January 22 between the Transport Ministry and representatives of Žilinská Diaľnica.

 

Under this project, which is regarded as the most technically demanding, highway sections between Hričovské Podhradie and Lietavská Lúčka, Lietavská Lúčka and Višňové, Višňové and Dubná Skala, and Lietavská Lúčka and Žilina totalling 29 kilometres should be completed during the autumn of 2014, the ministry states on its website. An eight-kilometre-long tunnel between Višňové and Dubná Skala is part of the project. The target date for the financial close is May 2010, according to SITA.

 


More articles

Slovakia to get more shopping malls

Slovakia to get more shopping malls
5 days ago

Construction and expansion of shopping centres in Slovakia will continue. “Slovakia expects extensive construction and expansion of shopping centres in 2017 and 2018,” said Katarína Paule, head of the retail team at Cushman & Wakefield in Slovakia. “In 2017, there will be as much as 56,258 square meters in total to be completed, with 83 percent being new shopping centres, and 17 percent planned expansions of already existing projects.”

Arete Invest to put €30 million into real estate projects in Slovakia

Arete Invest to put €30 million into real estate projects in Slovakia
1 week ago

Arete Invest, a Czech investment fund focused on real estate, plans to invest around €30 million in Slovakia in 2018. It is considering new construction on industrial premises it already owns as well as new acquisitions. The company sees great potential in the Slovak market.

New shopping centre Slnečnice Market will open in late November

New shopping centre Slnečnice Market will open in late November
2 weeks ago

The new residential area of Slnečnice that is being built on the outskirts of Petržalka will get a new shopping centre, Slnečnice Market. There will be more than 30 shops, restaurants, cafés, a fresh produce market and others on 8,300 square metres. The first phase of the opening is planned for November 30 and the second for the following weeks. The centre will also offer 195 parking places for the public.

Cvernovka becomes Zwirn

Cvernovka becomes Zwirn
2 weeks ago

The new development that is rising on the premises of the former Bratislava Thread Factory, colloquially known as Cvernovka, is getting a new name – Zwirn. The new name symbolises a move forwards as well as connecting the whole zone with its history, claims the Slovak-Finnish developer YIT Slovakia. The factory has changed names several times over the years. It was called Pozsony Csernagyar, Pressburger Zwirnfabrik, Bratislavská Cvernová Továreň, Danubia, and Závody MDŽ 8. Marca.

Refurbishment of Trnavské Mýto has started

Refurbishment of Trnavské Mýto has started
1 month ago

A thorough refurbishment of the Trnavské Mýto pedestrian underpass, a dilapidated but significant hub of public transport in Bratislava, was launched on October 16. Works are projected to last nine months with the plan being to open the renewed underpass in mid July 2018. The work will be divided into phases in order that people can use the underpass during its revitalisation. The Immocap Group are the company responsible for the refurbishment and will invest €2.5 million into the project while Bratislava city council will provide €1.2 million for the purchase and installation of new escalators and lifts.

Coca-Cola has sold its production premises near Piešťany

Coca-Cola has sold its production premises near Piešťany
1 month ago

Coca-Cola HBC Česko a Slovensko, a company within the Coca-Cola Hellenic group, has sold its production and distribution premises of 155,000 square metres, including all technologies, in Lúka near Piešťany to Priemyselný Areál Lúka. The deal followed the decision of Coca-Cola to move its production from Slovakia to Austria. Both parties agreed not to disclose the value of the transaction.

YIT launches sale of apartments in third phase of former brewery development in Bratislava

YIT launches sale of apartments in third phase of former brewery development in Bratislava
1 month ago

Slovak-Finnish company YIT Slovakia has launched the sale of apartments in the third phase of the STEIN2 project in Bratislava. For the first time, there are apartments with terraces on offer. The final building approval is expected during the last quarter of 2018.