Rodina LIVING



Highway PPP projects go on, despite complications
NA, By Jana Liptáková

Highway PPP projects go on, despite complicationsConstruction of the Banská Bystrica’s bypass is part of the so-called second PPP package. Photo: Sme – Ján Krošlák

Slovakia is placing a lot of hope in its public-private partnership (PPP) projects to build highways. Not only are these intended finally to link the east and west of the country with an unbroken multi-lane highway and hence bring new business opportunities eastwards, but they should also provide orders for construction companies, thus helping to keep them afloat and their workers employed. However, the economic crisis has slowed down and complicated the whole process.

 

“Slovakia undertook preparation for highway PPP projects as early as 2007, when intensive preparation of public procurement for concessionaires for three PPP packages started,” Irma Chmelová, executive director of the PPP Association, told The Slovak Spectator. “The financial crisis, which has significantly changed conditions for provision of loans on the market, has complicated the situation.”

 

Of the three PPP packages for highway construction in Slovakia, the so-called second package was the first to achieve financial close, in August 2009. The project covers financing, construction, operation and maintenance of sections of the R1 dual-carriageway, specifically Nitra-Selenec, Selenec-Beladice, Beladice-Tekovské Nemce and the northern bypass around Banská Bystrica. The financial structure of the PPP contract, which will continue for more than 30 years, represents a total value of over €1.7 billion. Shareholders in Granvia, the consortium awarded the contract, will contribute €149 million, the European Bank for Reconstruction and Development is contributing €200 million and the rest is being provided by 12 banks. Under this project, the consortium will build a total of 52 kilometres of the dual-carriageway. Based on the concession contract with Granvia, the state will pay the consortium for construction of the sections and, after completion, their operation and maintenance for the following 30 years.

 

Construction work started in September 2009 and the individual sections should gradually be put into operation during 2011 and 2012. They are scheduled to be completely approved for public use by the end of January 2013.

 

According to Chmelová, the project also won a prestigious award from PFI magazine, the PFI Award in the category Infrastructure Deal of the Year in Europe, where it succeeded despite stiff competition.

 

“Compared with the pre-crisis situation banks are more cautious, they are lending less, for a shorter period of time and at higher interest,” Chmelová told The Slovak Spectator. “On the other hand, PPP projects’ contracts contain a provision on refinancing based on which, in case conditions for financing improve in the future, the more expensive financing will be replaced by cheaper [financing].”

 

The financial crisis has also resulted in stronger involvement by international financial institutions such as the European Investment Bank and the European Bank for Reconstruction and Development in PPP projects, according to Chmelová.

 

“Even though there are signals that the situation in financial markets is improving, it is necessary to wait for confirmation of these indications in real transactions,” she said.

 

After a number of postponements the next deadline for the financial close of another PPP package, this one known as the first PPP package, is the end of April. This is because the concessionaire, Slovenské Diaľnice, has so far failed to obtain financing for the project to construct 75 kilometres of the D1 highway, from Dubná Skala (near Vrútky) to Svinia (Prešov district), according to the SITA newswire. However, preparatory work on the sections has already started and will continue.

 

“Certain complications have occurred in negotiation over some problems and provisions with the European Commission and subsequently the European Investment Bank,” said Minister of Transport, Postal Services and Telecommunications Ľubomír Vážny, as quoted by SITA, after a March 3 cabinet session which agreed to the postponement of the financial close until the end of April.

 

The postponement relates to environmental issues arising from revision of the Environmental Impact Assessment Act.

 

The Slovak parliament adopted the revision, into which the Environment Ministry incorporated comments from the European Commission, which had objected to discrimination against private persons expressing their views on the environmental impact of large construction projects, on March 9.

 

Based on this revision, the public will have more space for participation in the approval process of some public and private projects. After the revision becomes effective, some private individuals, corporate entities, civil initiatives and associations and organisations supporting environmental protection will be able to have a say in environmental projects, something which was previously partially restricted. However, environmental organisations complain that within the amending proposals, parliament approved a provision cancelling completely the right of the public to obtain information about approval of nuclear power plants and equipment, according to SITA.

 

The European Investment Bank is supposed to provide €1 billion for the first PPP highway project, while an additional €2.5 billion is needed from private banks, according to the Pravda daily.

 

Transport Minister Vážny signed the concession agreement with representatives of the Slovenské Diaľnice consortium, led by French company Bouygues Travaux Publics SA, in April 2009. The project’s sections of the D1 highway, connecting Bratislava with Košice via the so-called northern route, should be put into trial operation by July 2013.

 

The concession agreement for construction of other D1 sections via the third PPP package was signed on January 22 between the Transport Ministry and representatives of Žilinská Diaľnica.

 

Under this project, which is regarded as the most technically demanding, highway sections between Hričovské Podhradie and Lietavská Lúčka, Lietavská Lúčka and Višňové, Višňové and Dubná Skala, and Lietavská Lúčka and Žilina totalling 29 kilometres should be completed during the autumn of 2014, the ministry states on its website. An eight-kilometre-long tunnel between Višňové and Dubná Skala is part of the project. The target date for the financial close is May 2010, according to SITA.

 


More articles

Bratislava to get a new shopping mall

Bratislava to get a new shopping mall
1 week ago

While Bratislava already accommodates almost 30 shopping centres, another one is on the horizon. Macho Consulting, a company that has been devoted especially to residential projects in the past, will build Matrix Mall in the more or less industrial zone of Bratislava in the borough of Nové Mesto. The shopping centre on the corner of Magnetova and Vajnorská streets, close to the Vozovňa Nové Mesto depot, will offer retail and office space.

City Arena shopping centre in Trnava changes hands

City Arena shopping centre in Trnava changes hands
2 weeks ago

Trnava-based tycoon Vladimír Poór has sold the recently opened City Arena shopping centre in Trnava to Peter Korbačka, the head of the board of directors of the developer J&T Real Estate. The latter already owns the Eurovea shopping centre in Bratislava. Neither the price nor other details of the transaction have been disclosed.

New Apollo to replace flawed Apollo Business Centre

New Apollo to replace flawed Apollo Business Centre
3 weeks ago

The emptied defective Apollo Business Centre 1 in Bratislava will be replaced by a brand-new construction. The developer HB Reavis estimates the launch of demolition work for the end of 2018. Construction work on the new business centre, the Nové (new) Apollo should start in late 2019 and be complete in 2021. Exact dates will depend on permission processes.

Make-over for park in Bratislava’s Old Town

Make-over for park in Bratislava’s Old Town
3 weeks ago

Bratislava is to get another revitalised public space. The developer Corwin is renewing a neglected park on Kmeťovo Square in the Old Town borough. Works on the park, which lies between Bernolákova and Wilsonova Streets, have already started and should be complete by the beginning of the summer.

Main industrial regions report lack of accommodation capacity

Main industrial regions report lack of accommodation capacity
1 month ago

The main industrial regions in Slovakia are reporting a lack of accommodation capacity for workers. These are in the vicinities of industrial and logistics parks mostly along highways connecting Bratislava with Košice (D1), leading from Bratislava to the Czech Republic (D2) and the dual carriageway from Trnava to Banská Bystrica (R1).

Developer transforms former wine-making plant into a new centre for Bratislava’s Borough of Rača

Developer transforms former wine-making plant into a new centre for Bratislava’s Borough of Rača
1 month ago

The developer, belonging to the Bencont Group has already started pulling down the buildings and cleaning the three-hectare area. “We believe that Rínok Rača, which we will begin to construct soon, will be the new centre of the borough and will naturally fit into the life of its citizens,” said Martin Šimurda, representative of the developer Rínok Rača, as cited in the press report.

Bratislavans will be able to afford only a small flat with the new lending cap

Bratislavans will be able to afford only a small flat with the new lending cap
1 month ago

The new indebting rules tightened by the National Bank of Slovakia (NBS) will primarily impact citizens of the Slovak capital, Bratislava. They will be able to buy on credit, from an average wage, maximally a one-room flat in a new building or a two-room flat in an older block of flats. Other regions will be significantly less affected by the new lending cap, Poštová Banka has found out.